Planview Blog

Your path to business agility

Project Portfolio Management

5 Ways Technology Has Changed Project Management – Planview AdaptiveWork

Published By Team AdaptiveWork

As a means of judging a project’s progress and how well the initial project plan is being adhered to, Schedule Variance is one of the most useful and common metrics used. It can give quick insight into how well the project has performed so far and whether it is ahead of schedule or behind it. That sounds great and an obvious boon for any PM looking to gauge how their project is doing, but what is schedule variance exactly?

What is Schedule Variance & How to Work it Out?

Schedule variance is calculated by taking the Planned Value of your Project from the Earned Value. So, Earned Value (EV) – Planned Value (PV) = Schedule Variance (SV) or SV = EV – PV. So, to find the Schedule Variance of a project we also need to know it’s Earned Value and Planned Value.

  • Schedule Variance = Earned Value – Planned Value
  • Earned Value is the worth of the work completed so far, also known as the Budgeted Cost of Work Performed.
  • Planned Value is how much of your budget should have been spent so far, also known as the Budgeted Cost of Work Scheduled.
  • If the Schedule Variance is zero, the project is on schedule.
  • If the Schedule Variance is positive, progress is ahead of schedule.
  • If the Schedule Variance is negative, progress is behind schedule.
  • Schedule Variance % = Schedule Variance (SV) / Planned Value (PV)

To illustrate this better we’ll use an example. We’ll assume a project length of eight months, with a budget of $200,000. If four months have passed and you were due to have completed 50% or $100,000 of work but have only done $80,000 then the project is behind schedule by $20,000 or 20%.

(EV) 80,000 – (PV) 100,000 = (SV) -20,000

(SV) -20,000 / (PV) 100,000 = -20%

What Your Schedule Variance Says About Your Project

There are other metrics that can be used to inform clients or stakeholders of your project’s current progress, such as Cost Variance and a Schedule Performance Indicator but Schedule Variance is one of the most popular and widely understood. Especially after working out the Schedule Variance %, you will be able to provide an easily understandable headline figure for any project status report.

Increase your business agility with Planview AdaptiveWork’s project management software

What is Schedule Variance in Terms of Time Units?

Depending on the projected timeline of your project, it is also possible to use Schedule Variance to demonstrate in hours, days or weeks how far ahead or behind your project is. To do so, decide on the time units you want to use and then work out how many there are in your project to get Total Project Time (TPT). Using the previous example, we have eight months, which is, for the sake of the example, 32 weeks or 160 days. We will choose days as our measurement unit. Of these eight months, four have passed, which gives us the Time Elapsed (TE). Then, we use the formula:

SV x Time Elapsed (TE) x Total Project Time (TPT) = Schedule Variance in terms of time units

-20% x 50% x 160 = -16

So, from this we can see that the project is so far negative 16 days away from being on schedule, i.e. 16 days behind.

Whichever way you choose to present the Schedule Variance of your project, knowing how to find it gives you a great option for providing clarity to your clients and stakeholders.

Related Posts

Written by Team AdaptiveWork