Critical Path Method

To determine the critical path of a project three major factors are required:

  • a full list of activities required to complete the project
  • the duration of each work item
  • work item dependencies.


The critical path is then determined by calculating the longest path of planned activities to the end of the project, meaning, the earliest and latest that each activity can start and finish without lengthening the project.




Related Information