New in Issue Management

Track Work required to resolve an issue directly in the Issues page.



  • Work, Actual Effort and Remaining Effort represent correspondingly estimated effort required for issue resolution, already invested actual effort and remaining effort.
  • Values of these fields can be: 
    » Set manually by the user.
    » In case an issue is linked to related work, the Work, Actual Effort and Remaining Effort of the issue will automatically be updated with progress reported on related work items unless their values were not manually set by the user.
  • Work Variance is calculated as (Work – Actual Effort)