Tasks Reporting Policy



    1. Select the Admin option from MORE
    2. Click on System settings tab
    3. Expand Task Completion Reporting Policy group to update appropriate settings
    4. Expand Task Completion Reporting Policy group to update appropriate settings
    5. Define how you report on project progress:
      Set Enable reporting actual and remaining effort to allow reporting in actual and remaining efforts or Set Enable reporting completion percentage to allow reporting in percentage
    6. Progress report by email settings
    7. Click on Save to apply the changes


  • Depending on your organization policy, your project team would be able to report progress of the work, based on % completion, actual and remaining efforts or both
  • You must click on the Save button in order to apply the changes to the system